What is going on
Network Controller Ana Kovac has written switching program SP-26-0921 for the BUN-12 outage on Tuesday 16 September to replace pole 119. The program has eighteen steps: it transfers load to feeder BUN-14 by closing ABS-130, opens ABS-118 and ABS-122 to isolate the section, proves de-energised and applies earths at poles 118 and 122, then issues access authority EAA-26-2210 and restores in reverse. The network diagram shows a 22 kV spur to a dairy substation between poles 120 and 121 with its own drop out fuses, and a recent operation record shows ABS-130 was left open for a fault last month. Customer notification says 8:00 am to 2:00 pm.
Subject: Check switching program SP-26-0921 before Tuesday
I have written switching program SP-26-0921 for the BUN-12 outage on Tuesday and need an independent check. Please validate it against the network diagram and the isolation and earthing requirements on access request EAA-26-2210: confirm the load transfer to BUN-14 through ABS-130 happens before ABS-118 opens, that the earths at poles 118 and 122 bound the work area, and that the customer notification matches the outage window. Record your check in the switching program register. If you find a problem, do not sign it; send it back to me with the step number.
Your brief
Independently check the switching program against the network diagram, the access request and the switching procedure, identify any step that is wrong, missing or out of sequence, decide whether to validate or return it, and record your check in the switching program register with the reasons for your decision.
Work through it
You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.
What someone in this role would produce
- Marked up copy of the switching program with your check on every step
- Switching program register entry with the validation decision and reasons
- Note to the controller summarising the findings