Plan a transmission tower climbing inspection and hardware replacement

You are a Transmission Line Worker and crew planner in Transmission Lines.

Simulated workplaceIntermediate missionCAQA Gridworks Networks

What is going on

The client has confirmed a two day outage of the Morwell to Hazelwood 220 kV line on 22 and 23 September for work order WO-26-4388. A ground inspection in July found corroded suspension hardware on phase A of structure 47 and missing cotter pins on phase C. The client's transmission control will perform the terminal switching; Gridworks must write the program for its own portable earths at structures 44 and 52 and request the access authority. The crew of six includes two climbers whose tower rescue currency expires on 20 September. A parallel 220 kV line on the same easement remains live throughout, and the structures are 42 metres high in open farmland with a farm access track.

Callum O'Shea, Transmission Lines Manager
Subject: Structure 47 climbing inspection and hardware replacement on 22 September

The Morwell to Hazelwood 220 kV outage for structures 44 to 52, work order WO-26-4388, has been confirmed by the client for 22 and 23 September. I want you to plan the climbing inspection of structure 47 and the replacement of the corroded suspension hardware on phase A. Prepare the job risk assessment with the tower rescue plan, confirm every climber's authorisation and rescue currency on the register, finish the draft switching program SP-26-0925 for our portable earths, and submit the access request. Our tower rescue drill is due before this job; schedule it.

Your brief

Plan the climbing inspection and hardware replacement safely: prepare the job risk assessment with the tower rescue plan and the induced voltage controls from the live parallel line, confirm every climber's authorisation and rescue currency, complete the switching program for the portable earths, submit the access request and schedule the rescue drill so that the job can proceed on 22 September.

Work through it

You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.

What someone in this role would produce

  • Job risk assessment with tower rescue plan and induced voltage controls
  • Authorised persons check and rescue drill booking
  • Completed switching program SP-26-0925 submitted for checking
  • Access authority request in the register
  • Work plan and materials list on the work order

Printing this is a record of what you explored. It is not a certificate or a qualification.