Act as access recipient for a 22 kV pole replacement
You are a Line Worker authorised as a high voltage access recipient in Overhead Distribution.
What is going on
Condemned pole 119 on Buninyong feeder BUN-12, work order WO-26-4410, is to be replaced on Tuesday 16 September with a 22 kV and low voltage outage from 8:00 am to 2:00 pm. Access request EAA-26-2210 is in the register and switching program SP-26-0921 is being checked. The pole is on the Midland Highway shoulder, requiring traffic management, and the low voltage mains supply a dairy that has been told to run its generator. The crew of four includes a second year apprentice, and the elevated work platform and a pole borer are on site. A second 22 kV feeder crosses the road two spans away and remains live.
Subject: Pole 119 replacement on BUN-12 next Tuesday, you are access recipient
I want you to act as access recipient for the pole 119 replacement on Buninyong feeder BUN-12, work order WO-26-4410, next Tuesday. The access request EAA-26-2210 is in the register and the switching program SP-26-0921 is with the controller for checking. Prepare the tailgate briefing and job risk assessment, including the traffic management on the Midland Highway and the elevated work platform rescue plan, take the authority from the controller with a proper read back, brief the crew, and cancel it correctly when we are done. Read the access authority procedure first.
Your brief
Prepare the crew and site for the outage, take the electrical access authority from the network controller with a correct read back, hold it responsibly for the duration of the work including the working earths and the live adjacent feeder, and cancel it correctly so that restoration can proceed, all in line with the access authority procedure.
Work through it
You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.
What someone in this role would produce
- Completed tailgate briefing and job risk assessment with rescue plan
- Completed electrical access authority form with issue, sign on and cancellation
- Updated access and permit register entry
- Updated work order with hours and authority number
Printing this is a record of what you explored. It is not a certificate or a qualification.