Plan the GT2 combustion inspection outage

You are the Outage Planner reporting to the Outage Planning Manager.

Simulated workplaceAdvanced missionCAQA Powergen Station

What is going on

GT2 tripped on 5 September on exhaust temperature spread and the trip investigation recommends bringing the combustion inspection forward from next year to November. OUT-26-11 sits in the schedule as a proposal for nine days from 23 November with an estimate of 1.42 million dollars. The scope must be built from the open defects on GT2, the trip investigation, the inlet filter change and the thermocouple replacement. The GT1 and steam turbine outage runs from 5 October and shares the crane and the scaffold contractor. The market operator needs the availability submission and the Station Manager will approve the plan at the meeting on 24 September.

Nadine Faulkner, Outage Planning Manager
Subject: GT2 combustion inspection outage proposal

After the exhaust spread trip we need to bring the GT2 combustion inspection forward from next year to November. OUT-26-11 is in the schedule as a proposal only. Please build the outage plan to the outage planning procedure: scope from the open defects and the trip investigation, a critical path with the isolation windows, a cost estimate with a deferral option, and the market submission. Graham wants to approve it at the planning meeting on 24 September so I need the pack by the 22nd.

Your brief

Build the outage plan to the outage planning procedure: scope from defects and the investigation, a critical path with isolation and switching windows, a resourced schedule, a cost estimate with a deferral option, the market submission and an approval pack for the Station Manager.

Work through it

You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.

What someone in this role would produce

  • Scope list linked to work orders
  • Critical path schedule with resources
  • Cost estimate with deferral option
  • Updated outage record and market submission draft
  • Approval pack

Printing this is a record of what you explored. It is not a certificate or a qualification.