Quote a distribution board replacement for an owners corporation
You are an Estimator and Project Electrician in Electrical Contracting.
What is going on
The thermal imaging survey at Harbourview Apartments, job J-26-1152, found two hot joints on the neutral bar of the level 8 distribution board. The owners corporation has asked for a quotation to repair the joints immediately and to replace the level 8 board with a new board that provides residual current protection on every final sub-circuit. The board supplies twelve apartments' common area circuits, the level 8 corridor lighting, fire door holders and a lift lobby air conditioner. Any outage must be arranged with the building manager and residents notified forty-eight hours ahead. The riser is tight and access is through a locked cupboard. The Electrical Contracting Manager will review the draft before it is sent.
Subject: Quote for the Harbourview level 8 board repairs and upgrade
Our thermal survey at Harbourview, job J-26-1152, found two hot joints on the level 8 distribution board and the owners corporation has asked for a quotation to repair the joints and replace the board with a new one with residual current protection on every circuit. Use the quotation template, plan the installation with the outage and access arrangements the building manager will need, price the materials and labour, and list the exclusions clearly. I want to review the draft before it goes out next Friday.
Your brief
Prepare a complete quotation using the quotation template: define the scope and sequence for the repair and the replacement, plan the outage and access, select materials and estimate labour with the pricing schedule, state the exclusions and assumptions, describe the testing and certification, and update the job records.
Work through it
You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.
What someone in this role would produce
- Completed quotation on the template with scope, price, exclusions and program
- Materials list and labour estimate
- Outage and access plan
- New job board record and cover note to the customer