Rebuild next week's production schedule after the mill outage
You are the production planner in Planning, Stores and Dispatch.
What is going on
The hammer mill will be down on Monday and Tuesday for the hammer and screen change and blender 2 is out of service until the interlock is replaced and tested. Together these take about 6,000 bags out of next week's plan. Two orders cannot move: the Brightline Hardware Group private label adhesive, 4,200 bags due Thursday, and the Northern Rivers Tiling Cooperative order of grout and adhesive, 2,600 bags due Friday. The stock records shows some cover on standard adhesive but almost none on the private label product. Townsville has spare capacity on the render range. Lucy Anand wants a rebuilt schedule with the impact on other orders, stock cover and the overtime or Saturday shift required, ready for Monday's planning meeting.
Subject: Reschedule the week after the mill outage
The hammer mill will be out for two days for the hammer and screen change and the interlock work on blender 2 has taken it out of service. That knocks about 6,000 bags out of the plan for next week. I need you to rebuild the weekly schedule so that the Brightline Hardware Group private label order and the Northern Rivers Tiling Cooperative order ship on time, check stock cover in the stock records and tell me which orders will move and what overtime or Saturday shift is needed. Bring the draft to the planning meeting on Monday.
Your brief
Rebuild the weekly production schedule around the reduced capacity so that the two fixed orders ship on time, using stock cover, resequencing, Townsville capacity and additional shifts where justified, and present the schedule with the impact on other orders and the resources needed.
Work through it
You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.
What someone in this role would produce
- Rebuilt weekly production schedule
- Stock cover analysis
- Impact list of moved orders with new dates
- Resource request for overtime or Saturday shift