Build the shutdown schedule and material readiness report

You are the Production Planner in the Engineering Office.

Simulated workplaceAdvanced missionCAQA Ironbark Engineering

What is going on

The Mount Errol Quarries seventy-two hour shutdown starts at 6:00 am on 13 October 2026 and the plant must be handed back by 6:00 am on 16 October. The approved shutdown plan gives the scope, crews and sequence but not a shift-by-shift schedule. Materials are arriving against the delivery schedule: the bearings and chute liners are in, the jaw liner certificate is still requested, and the mobile welding unit is under repair after a yard incident. Jodie Ferrante needs a detailed schedule loaded against job card JC-26-0420, a material and equipment readiness check and a one-page risk summary for the General Manager so problems are fixed before mobilisation.

Jodie Ferrante, Engineering Office Manager
Subject: Shutdown schedule and material deliveries

Bree has approved the Mount Errol shutdown plan and I need the detailed schedule built from it. Break the three days into shifts and tasks per crew, check that the materials on the delivery schedule are received in the materials register, and flag anything missing or in quarantine. The jaw liner certificate is still outstanding. Update the job card JC-26-0420 with the schedule and give me a one-page summary of risks to the handover time.

Your brief

Build a shift-by-shift schedule for the shutdown from the plan, check material, certificate and equipment readiness in the registers, estimate labour hours by crew against the quoted hours, and write a one-page risk summary with actions to protect the handover time.

Work through it

You do not need to do it all. Doing a few of these will show you what the work is like. Your ticks and notes stay on this device.

What someone in this role would produce

  • Shift-by-shift shutdown schedule with critical path
  • Labour hours estimate compared with the quoted hours
  • Material and equipment readiness report
  • One-page risk summary with actions
  • Updated job card JC-26-0420